Construction & handover
From the Dubai Land Department project register.
- Status
- Under construction
- Planned completion (DLD)
- March 2026
- Construction progress
- 64% inspected 15 Sep 2026
- Developer
- Swank
- Homes
- 42 villas / townhouses
- Registered project value
- AED 103.1M
- Escrow account
- Registered
- DLD project number
- 2974
G+2 MASTER PLAN COMMUNITY OF 37 VILLAS.
The completion date originally registered with DLD has passed. Developers can extend it with DLD approval, so ask us for the latest handover schedule.
Legal developer: SWANK REAL ESTATE DEVELOPMENT L.L.C · Escrow account no. 3718467862003
What off-plan homes sell for in Wadi Al Safa 3
Registered off-plan sales across Wadi Al Safa 3 this year, a guide to what a launch here is likely to be priced at.
Other new projects in Wadi Al Safa 3
| Project | Developer | Homes | Handover | Built |
|---|---|---|---|---|
| The Woodland Residences | Amis | 30 | Apr 2026 | 75% |
| Estrella by Nexus | Nexus Capital | 60 | May 2026 | 46% |
| The Waterside Villas by Ellington | Ellington | 17 | Jun 2026 | 45% |
| Tulip Oasis 11 39 sales | Ame | 108 | Jun 2026 | 93% |
| Living Legends Phase 6 138 sales | Dawn | 955 | Jul 2026 | Not reported |
| The Lakeview Villas by Ellington | Ellington | 22 | Aug 2026 | 20% |
| The Beachfront Villas by Ellington | Ellington | 21 | Aug 2026 | 47% |
| Koyo Residence by Fuji Properties | Fuji | 44 | Sep 2026 | 31% |
| Mangrove 2 | Mangrove | 18 | Sep 2026 | 38% |
| High Best Tower | True Future | 88 | Nov 2026 | 91% |
Common questions
When is the handover of Lua Residences?
The completion date registered with Dubai Land Department is March 2026. The latest DLD inspection (15 Sep 2026) recorded 64% construction progress. Developers can revise this date with DLD approval.
Who is the developer of Lua Residences?
Lua Residences is developed by Swank (registered as SWANK REAL ESTATE DEVELOPMENT L.L.C).
Is Lua Residences registered with DLD?
Yes. It is DLD project number 2974, with escrow account 3718467862003. Current status: active.
How much do off-plan homes cost in Wadi Al Safa 3?
Off-plan homes in Wadi Al Safa 3 sold for a median of AED 1,946 per sq ft in 2026, across 672 registered sales.
Lua Residences, Wadi Al Safa 3 कहाँ है?
Wadi Al Safa 3 के लिए कीमत अलर्ट पाएँ
WhatsApp पर छोटा मासिक अपडेट: नई पंजीकृत कीमतें, बिक्री और लॉन्च।
सलाहकार से बात करें
इस पर साफ़ जवाब पाएँ
बताइए आप क्या ढूँढ रहे हैं। हम एक कार्य-घंटे के भीतर विकल्प, हाल की पंजीकृत कीमतें और पूछने लायक सवाल भेजते हैं।
- ✓ कीमतें DLD पंजीकरण से जाँची गईं
- ✓ RERA-पंजीकृत सलाहकार (ORN 1653674)
- ✓ कोई बाध्यता नहीं, कोई स्पैम नहीं