Sartoria: موعد التسليم ونسبة الإنجاز
Sartoria by Pinnacle A K S
الإجابة المختصرة
Sartoria is a residential project by Pinnacle A K S in Al Hebiah Fourth, registered with Dubai Land Department as project 3853 with 224 units. The latest DLD inspection (8 Oct 2026) recorded 51% construction progress, and the registered completion date is October 2027.
آخر تحديث رقم ريرا للمكتب 1653674
Source: Dubai Land Department project register. This page currently covers 811 residential and mixed-use projects that were registered, started, due or completed in 2026; earlier launches are added as the full register is loaded.
الأرقام والجداول التفصيلية في هذه الصفحة منشورة باللغة الإنجليزية.
Construction & handover
From the Dubai Land Department project register.
- Status
- Under construction
- Planned completion (DLD)
- October 2027
- Construction progress
- 51% inspected 8 Oct 2026
- Developer
- Pinnacle A K S
- Homes
- 224 units
- Registered project value
- AED 58M
- Escrow account
- Registered
- DLD project number
- 3853
1B+G+16+Roof
Legal developer: PINNACLE A K S REAL ESTATE DEVELOPMENT L.L.C · Escrow account no. 019500000929
What off-plan homes sell for in Al Hebiah Fourth
Registered off-plan sales across Al Hebiah Fourth this year, a guide to what a launch here is likely to be priced at.
More by Pinnacle A K S
| Project | Area | Homes | Handover | Built |
|---|---|---|---|---|
| Vitalia by Pinnacle | Palm Jumeirah | 45 | Jun 2026 | 21% |
Other new projects in Al Hebiah Fourth
| Project | Developer | Homes | Handover | Built |
|---|---|---|---|---|
| Elysian Mansions | Majid Al Futtaim | 35 | Mar 2025 | Not reported |
| Mag 777 50 sales | Dng | 266 | Jan 2026 | 67% |
| Sportz By Danube 53 sales | Danube | 1,110 | Mar 2026 | Not reported |
| Binghatti Haven 88 sales | Binghatti | 501 | Mar 2026 | 76% |
| Urban Park Residences 27 sales | Urban Venture | 187 | Apr 2026 | 68% |
| Lime Light Twin Towers | Lime Light | 734 | Jun 2026 | Not reported |
| Alaya | Majid Al Futtaim | 46 | Jul 2026 | Not reported |
| LANAI Island | Majid Al Futtaim | 13 | Sep 2026 | Not reported |
| Oasis Tower 2 | Pal | 444 | Jun 2027 | 74% |
Common questions
When is the handover of Sartoria?
The completion date registered with Dubai Land Department is October 2027. The latest DLD inspection (8 Oct 2026) recorded 51% construction progress. Developers can revise this date with DLD approval.
Who is the developer of Sartoria?
Sartoria is developed by Pinnacle A K S (registered as PINNACLE A K S REAL ESTATE DEVELOPMENT L.L.C).
Is Sartoria registered with DLD?
Yes. It is DLD project number 3853, with escrow account 019500000929. Current status: active.
How much do off-plan homes cost in Al Hebiah Fourth?
Off-plan homes in Al Hebiah Fourth sold for a median of AED 2,130 per sq ft in 2026, across 26 registered sales.
أين يقع Sartoria, Al Hebiah Fourth؟
احصل على تنبيهات الأسعار في Al Hebiah Fourth
تحديث شهري قصير عبر واتساب: أحدث الأسعار المسجّلة والصفقات والإطلاقات.
تحدّث إلى مستشار
احصل على إجابة واضحة
أخبرنا بما تبحث عنه. نرد خلال ساعة عمل واحدة بخيارات وأسعار مسجّلة حديثاً والأسئلة التي تستحق الطرح.
- ✓ أسعار مُتحقَّق منها مقابل تسجيلات الدائرة
- ✓ مستشارون مسجّلون لدى ريرا (رقم المكتب 1653674)
- ✓ دون التزام ودون رسائل مزعجة